Site Operations and Maintenance U.S. Department of Energy

Staff are on site 7 days per week performing security and maintenance activities. Tailings excavation and conditioning operations run 4 days a week.

In addition to excavating and conditioning mill tailings, the Project has excavated and sorted a portion of the mill building debris that was buried in the southern end of the tailings pile. Some debris has been shipped in containers modified to carry this type of material.

The Moab Project ships two trains a week. During the month of October, more than 37,500 tons of tailings were shipped to Crescent Junction for disposal, for a total to date of almost 8,859,000 tons shipped.

Animated Line